Project Budget
IBGP IS
Below are the budget items for efforts leading up to the delivery
of the IBGP information system on August 30, 2000, totaling $8,677.
This covers all the tasks identified in the task list for Phase 1 only.
- Personnel
- Professor Mamrak: $150/hour * 20 hours = $3,000.
- Sheetal Pole, CIS GRA: Salary plus fringes is $26,187/(48 weeks) at
50% time. Her effort was 100% for 20 days or the equivalent of 50%
for 40 days or 8 weeks. 8/48 = .17 * $26,187 = $4,452.
- Mary Zando, Access Consultant: $75/hour * 3 hours = $225.
- Equipment: use of PC, network connect fees, computer services
at $1000.
We received $8,796 for this work.
COMPH IS
To support the transformation of the IBGP IS to the COMPH IS, Allan
agreed to support three additional GRA quarters at a cost of $13,248.
This work includes
- Enhancement of the database to include all the new tables and
fields required. The database now includes 64 tables containing 271
fields.
- Enhancement of the Switchboard to include an input capability
for all the new tables and fields.
- Upload of data in Word documents, for appropriate reports (3,
8, 9, 10, 11,18).
- Automatic report generation for select reports (all 22,
excluding 4-7, 14, and 17). We are excluding some reports because
either we decided not to store the relevant data or automated
generation is not applicable.
COMPH IS: Extensions
Even after completion of the work above, several requests are
outstanding for various reports and queries. Allan agreed to support
a GRA for the summer quarter 2001 ($4415.25) to complete this work. We
will confer at the end of the quarter to determine a need for
continued support.
The total budget for the specified work is $22,485.25.
Sandy Mamrak